Dept. of Trans. PROGRESS Serial No. Contract No. 16-116-11-15 07-3P7004 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 76% Location: Federal Project: 07-VEN-33-11.3/11.3 NONE Progress payment No. 009 Payment period ending: 04-20-16 MGP CONSTRUCTION PO BOX 355 UPLAND CA 91785 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 780,576.53 107,904.72 2. a. Extra Work 25,915.91 22,454.15 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 806,492.44 130,358.87 5. Mobilization 6. Total Work Completed 806,492.44 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 796,492.44 130,358.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 130,358.87