Dept. of Trans. PROGRESS Serial No. Contract No. 19-113-12-41 07-3P7904 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 77% Location: Federal Project: 07-LA-1-41.7/41.7 NONE Progress payment No. 006 Payment period ending: 04-20-19 PROCON BUILDERS INC 9526 TOPANGA CANYON BLVD CHATSWORTH CA 91311 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 193,503.40 -20,315.00 2. a. Extra Work 118,206.12 111,595.84 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 311,709.52 91,280.84 5. Mobilization 15,700.00 0.00 6. Total Work Completed 327,409.52 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 327,409.52 91,280.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 91,280.84