Dept. of Trans. PROGRESS Serial No. Contract No. 16-264-15-16 07-3W0504 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 55% Location: Federal Project: 07-LA-91-6.0/R13.8 NONE Progress payment No. 003 Payment period ending: 09-20-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 428,524.50 402,174.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -211,682.37 4. Earned Subject to Retention 428,524.50 190,492.13 5. Mobilization 66,500.00 0.00 6. Total Work Completed 495,024.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 495,024.50 190,492.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 190,492.13