Dept. of Trans. PROGRESS Serial No. Contract No. 18-022-12-32 07-3W1204 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 3% Location: Federal Project: 07-LA-1-35.2/59.9 NONE Progress payment No. 002 Payment period ending: 01-20-18 CAL STRIPE INC 2040 E STEEL RD COLTON CA 92324 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,732.50 13,650.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 14,732.50 13,650.00 5. Mobilization 10,500.00 10,500.00 6. Total Work Completed 25,232.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,232.50 24,150.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,150.00