Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-306-16-48 07-3W1204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-1-35.2/59.9 NONE Progress payment No. 005 Payment period ending: 06-21-18 CAL STRIPE INC 2040 E STEEL RD COLTON CA 92324 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 223,319.30 0.00 2. a. Extra Work 39,653.43 39,653.43 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 262,972.73 39,653.43 5. Mobilization 21,000.00 0.00 6. Total Work Completed 283,972.73 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 273,972.73 29,653.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,653.43