Dept. of Trans. PROGRESS Serial No. Contract No. 17-205-15-38 07-3W1804 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 25% Location: Federal Project: 07-LA-110-2.9/4.6 NONE Progress payment No. 002 Payment period ending: 07-20-17 VELARDE CONCRETE CONSTRUCTION INC 523 S. BRAND BLVD, #201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 200,705.07 193,734.17 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 200,705.07 193,734.17 5. Mobilization 59,375.00 59,375.00 6. Total Work Completed 260,080.07 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 260,080.07 253,109.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 253,109.17