Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-193-13-06 07-3W1904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-5-1.7/3.9 NONE Progress payment No. 011 Payment period ending: 06-22-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 420,987.05 0.00 2. a. Extra Work 39,577.43 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 460,564.48 0.00 5. Mobilization 56,000.00 0.00 6. Total Work Completed 516,564.48 7. Deductions 0.00 7,359.43 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 516,564.48 7,359.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,359.43