Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-219-14-04 07-3W2304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-5-20.3/R53.9 NONE Progress payment No. 010 Payment period ending: 05-21-18 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,159,852.26 0.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,159,852.26 0.00 5. Mobilization 120,000.00 0.00 6. Total Work Completed 1,279,852.26 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,279,852.26 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00