Dept. of Trans. PROGRESS Serial No. Contract No. 18-295-10-55 07-3W2404 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 59% Location: Federal Project: 07-LA-10-14.3/17.8 NONE Progress payment No. 003 Payment period ending: 10-20-18 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 157,120.00 97,810.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 157,120.00 97,810.00 5. Mobilization 101,250.00 33,750.00 6. Total Work Completed 258,370.00 7. Deductions -5,004.37 -1,668.12 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 253,365.63 129,891.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 129,891.88