Dept. of Trans. PROGRESS Serial No. Contract No. 19-022-10-02 07-3W2404 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 86% Location: Federal Project: 07-LA-10-14.3/17.8 NONE Progress payment No. 006 Payment period ending: 01-20-19 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 895,386.00 70,936.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 895,386.00 70,936.00 5. Mobilization 135,000.00 0.00 6. Total Work Completed 1,030,386.00 7. Deductions -8,672.50 4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,021,713.50 74,936.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74,936.00