Dept. of Trans. PROGRESS Serial No. Contract No. 18-022-12-35 07-3W3304 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 6% Location: Federal Project: 07-LA-2-10.6/12.7 NONE Progress payment No. 003 Payment period ending: 01-20-18 CALMEX ENGINEERING INC 2764 SOUTH VISTA AVE BLOOMINGTON CA 92316 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 278,684.00 249,813.58 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 278,684.00 249,813.58 5. Mobilization 57,038.14 57,038.14 6. Total Work Completed 335,722.14 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 325,722.14 296,851.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 296,851.72