Dept. of Trans. PROGRESS Serial No. Contract No. 18-022-12-37 07-3W3704 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 62% Location: Federal Project: 07-LA-105-R2.2/R13.5 NONE Progress payment No. 004 Payment period ending: 01-20-18 BC TRAFFIC SPECIALIST 638 W SOUTHERN AVE ORANGE CA 92865 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 234,921.00 0.00 2. a. Extra Work 13,432.95 13,432.95 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 248,353.95 13,432.95 5. Mobilization 15,625.00 0.00 6. Total Work Completed 263,978.95 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 253,978.95 3,432.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,432.95