Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-183-13-59 07-3W4304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-VEN-23-20.9/24.2 CSTP-P023(38) Progress payment No. 003 Payment period ending: 01-03-19 TORO ENTERPRISES INC PO BOX 6285 OXNARD CA 93031 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 731,477.45 4,500.00 2. a. Extra Work 9,574.00 9,574.00 b. Adustment Comp. 19,325.85 19,325.85 3. Materials on Hand 4. Earned Subject to Retention 760,377.30 33,399.85 5. Mobilization 42,000.00 0.00 6. Total Work Completed 802,377.30 7. Deductions -15,000.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 787,377.30 38,399.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,399.85