Dept. of Trans. PROGRESS Serial No. Contract No. 18-022-12-38 07-3W5404 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 94% Location: Federal Project: 07-LA-110-9.8/14.0 NONE Progress payment No. 004 Payment period ending: 01-20-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 460,317.87 170,005.05 2. a. Extra Work 3,965.48 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -9,707.37 4. Earned Subject to Retention 464,283.35 160,297.68 5. Mobilization 66,500.00 0.00 6. Total Work Completed 530,783.35 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 520,783.35 150,297.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 150,297.68