Dept. of Trans. PROGRESS Serial No. Contract No. 19-022-11-11 07-3W7104 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 92% Location: Federal Project: 07-VEN-23-3.2/11.4 NONE Progress payment No. 005 Payment period ending: 01-20-19 GUILLS INC 313 E ORANGE GROVE BLVD 290 PASADENA CA 91104 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,760,849.80 140,486.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,760,849.80 140,486.50 5. Mobilization 85,000.00 0.00 6. Total Work Completed 1,845,849.80 7. Deductions -12,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,833,849.80 130,486.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 130,486.50