Dept. of Trans. PROGRESS Serial No. Contract No. 18-267-09-10 07-3W9704 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 50% Location: Federal Project: 07-LA-105-R12.0/R15.9 NONE Progress payment No. 002 Payment period ending: 09-20-18 JABRE CONTRACTING INC 1813 MANZANITA LN MANHATTAN BEACH CA 90266 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,266.79 9,250.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 42,266.79 9,250.00 5. Mobilization 22,500.00 0.00 6. Total Work Completed 64,766.79 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 64,766.79 9,250.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,250.00