Dept. of Trans. FINAL Serial No. Contract No. 15-148-15-02 07-3X1804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-47-0.8/0.8 NH-47C0(4) Progress payment No. 009 Payment period ending: 01-22-15 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 134,441.04 0.00 2. a. Extra Work 41,995.23 0.00 b. Adustment Comp. 0.00 13,205.00 3. Materials on Hand 4. Earned Subject to Retention 176,436.27 13,205.00 5. Mobilization 32,000.00 0.00 6. Total Work Completed 208,436.27 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 208,436.27 13,205.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,205.00