Dept. of Trans. PROGRESS Serial No. Contract No. 11-207-13-01 07-3X2804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 100% 07-LA-107-1.1/1.2 Federal Project: 07-LA-107-0.0 NONE Progress payment No. 05 Payment period ending: 07-20-11 VELARDE CONCRETE CONSTRUCTION 523 SOUTH BRAND BOULEVARD SAN FERNANDO, CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 981,838.67 204,855.87 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 981,838.67 204,855.87 5. Mobilization 6. Total Work Completed 981,838.67 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 981,838.67 204,855.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 204,855.87