Dept. of Trans. PROGRESS Serial No. Contract No. 15-113-07-29 07-3X3504 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 47% Location: Federal Project: 07-LA-105-R2.6 ER-17E0(4) Progress payment No. 012 Payment period ending: 04-20-15 RSB GROUP INC 20331 LAKE FOREST DR #C13 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 567,857.15 0.00 2. a. Extra Work 13,542.36 5,476.15 b. Adustment Comp. 160,462.37 0.00 3. Materials on Hand 4. Earned Subject to Retention 741,861.88 5,476.15 5. Mobilization 80,000.00 0.00 6. Total Work Completed 821,861.88 7. Deductions -15,598.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 806,263.38 5,476.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,476.15