Dept. of Trans. PROGRESS Serial No. Contract No. 11-298-15-05 07-3X4004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 69% 07-VEN-118-10.9 Federal Project: 07-VEN-118-0.0 NONE Progress payment No. 04 Payment period ending: 10-20-11 D B GENERAL ENGINEERING & SITE DEVELOPMENT, INC. 2158 SCENICPARK STREET THOUSAND OAKS, CA 91362 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 220,027.96 35,334.82 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 220,027.96 35,334.82 5. Mobilization 6. Total Work Completed 220,027.96 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 220,027.96 35,334.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,334.82