Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-193-13-26 07-3X7114 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-60-R7.4/R8.1 STP-19P1(4) Progress payment No. 029 Payment period ending: 06-14-18 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,873,779.20 -30,715.00 2. a. Extra Work 760,409.48 44,811.33 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 6,634,188.68 14,096.33 5. Mobilization 490,000.00 0.00 6. Total Work Completed 7,124,188.68 7. Deductions -6,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,118,188.68 8,096.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,096.33