Dept. of Trans. PROGRESS Serial No. Contract No. 15-113-08-28 07-3X8204 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 16% Location: Federal Project: 07-LA-39-21.6/21.9 ER-45Y5(4) Progress payment No. 003 Payment period ending: 04-20-15 CHUMO CONSTRUCTION INC. 14425 JOANBRIDGE STREET BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 407,955.05 349,289.60 2. a. Extra Work 8,936.09 1,943.99 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 416,891.14 351,233.59 5. Mobilization 114,000.00 54,000.00 6. Total Work Completed 530,891.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 530,891.14 405,233.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 405,233.59