Dept. of Trans. PROGRESS Serial No. Contract No. 15-264-11-05 07-3X8204 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 21% Location: Federal Project: 07-LA-39-21.6/21.9 ER-45Y5(4) Progress payment No. 006 Payment period ending: 09-20-15 CHUMO CONSTRUCTION INC. 14425 JOANBRIDGE STREET BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 604,809.45 8,689.60 2. a. Extra Work 68,052.28 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 672,861.73 8,689.60 5. Mobilization 120,000.00 0.00 6. Total Work Completed 792,861.73 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 792,861.73 8,689.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,689.60