Dept. of Trans. PROGRESS Serial No. Contract No. 16-145-08-02 07-3X8204 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 21% Location: Federal Project: 07-LA-39-21.6/21.9 ER-45Y5(4) Progress payment No. 008 Payment period ending: 05-20-16 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 636,032.47 5,256.00 2. a. Extra Work 95,299.90 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 731,332.37 5,256.00 5. Mobilization 120,000.00 0.00 6. Total Work Completed 851,332.37 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 851,332.37 5,256.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,256.00