Dept. of Trans. PROGRESS Serial No. Contract No. 15-204-09-29 07-3X9304 PROGRESS PAYMENT VOUCHER %complete: %time: 0% 4% Location: Federal Project: 07-LA-118 NHPX-037(175) Progress payment No. 001 Payment period ending: 07-20-15 DBX, INC. 42024 AVENIDA ALVARADO, STE A TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,397.00 25,397.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 25,397.00 25,397.00 5. Mobilization 6. Total Work Completed 25,397.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,397.00 25,397.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,397.00