Dept. of Trans. PROGRESS Serial No. Contract No. 09-295-13-14 07-3Y0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 92% 07-VEN-33-24.8/26.9 Federal Project: NONE Progress payment No. 06 Payment period ending: 10-20-09 SUMMER CONSTRUCTION INC PO BOX 30 SANTA PAULA CA 93061 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 75,638.52 20,105.80 2.a. Extra Work 23,874.71 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 99,513.23 20,105.80 5. Mobilization 4,275.00 0.00 6. Total Work Completed 103,788.23 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 103,788.23 20,105.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,105.80