Dept. of Trans. PROGRESS Serial No. Contract No. 09-295-13-14 07-3Y0804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 63% 07-VEN-33-16.3/22.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-09 RSB GROUP INC 22600 G LAMBERT STREET NO 140 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,000.00 19,490.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 31,000.00 19,490.00 5. Mobilization 23,750.00 11,250.00 6. Total Work Completed 54,750.00 7. Deductions -11,879.75 -5,627.25 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 42,870.25 25,112.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,112.75