Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-15-33 07-3Y1304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 45% 07-VEN-33-32.5/48.4 Federal Project: NONE Progress payment No. 04 Payment period ending: 07-20-09 ELEVATION GENERAL ENGINEERING CONTRACTORS INC 2333 A STREET SANTA MARIA CA 93455 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 130,708.34 73,888.97 2.a. Extra Work 334.27 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 131,042.61 73,888.97 5. Mobilization 27,101.00 1,355.05 6. Total Work Completed 158,143.61 7. Deductions -9,101.10 -455.06 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 149,042.51 74,788.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74,788.96