Dept. of Trans. PROGRESS Serial No. Contract No. 08-234-13-08 07-3Y2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 69% 07-LA-118-R2.6/R12.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-20-08 PENHALL COMPANY P O BOX 310 ROGERS MN 55374 Escrow No. 02375 Total Estimate This Estimate 1. Contract Itms Without Mobil. 808,390.34 586,745.34 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 808,390.34 586,745.34 5. Mobilization 94,050.00 19,800.00 6. Total Work Completed 902,440.34 7. Deductions -1,420.00 -620.00 8. a.Contract Retentions -40,419.52 -18,255.02 b. Unsatisfactory Prog. -29,337.27 -29,337.27 c. Reduction after 95% Comp. 9. Total pay to Contractor 831,263.55 558,333.05 10. Reduction Amt to Escrow 11. Payment to Escrow 40,410.00 12. Net Pymt. this Estimate 558,333.05