Dept. of Trans. PROGRESS Serial No. Contract No. 09-146-14-42 07-3Y2104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 76% 07-LA-110-11.5/14.2 Federal Project: NONE Progress payment No. 08 Payment period ending: 05-20-09 J MC LOUGHLIN ENGINEERING 10641 FULTON COURT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,305,132.57 86,788.29 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,305,132.57 86,788.29 5. Mobilization 80,000.00 0.00 6. Total Work Completed 2,385,132.57 7. Deductions -650.00 0.00 8. a.Contract Retentions -115,256.63 -4,339.42 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,269,225.94 82,448.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,448.87