Dept. of Trans. PROGRESS Serial No. Contract No. 10-145-12-01 07-3Y3704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 34% 07-LA-10-R10.4/28.2 Federal Project: NONE Progress payment No. 02 Payment period ending: 05-20-10 POWELL CONSTRUCTORS 8555 BANANA AVENUE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 102,719.94 95,594.94 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 102,719.94 95,594.94 5. Mobilization 23,750.00 23,750.00 6. Total Work Completed 126,469.94 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 126,469.94 119,344.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 119,344.94