Dept. of Trans. PROGRESS Serial No. Contract No. 11-298-10-28 07-3Y4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 40% 07-VEN-101-8.9/11.5 Federal Project: ACNH-Q101(161) Progress payment No. 02 Payment period ending: 10-20-11 WINDSOR FUEL CO P O BOX 1029 PITTSBURG CA 94565 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 744,085.05 735,585.05 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 744,085.05 735,585.05 5. Mobilization 142,500.00 142,500.00 6. Total Work Completed 886,585.05 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 886,585.05 878,085.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 878,085.05