Dept. of Trans. PROGRESS Serial No. Contract No. 11-298-09-58 07-3Y5904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 83% 07-LA-91-R17.5/R17.5 Federal Project: NONE Progress payment No. 11 Payment period ending: 10-20-11 HIGHLAND CONSTRUCTION, INC. 133 NORTH PIXLEY STREET ORANGE, CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 140,894.50 39,547.45 2.a. Extra Work 532,718.09 107,082.84 b. Adjustment Comp. 59,100.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 732,712.59 146,630.29 5. Mobilization 53,000.00 0.00 6. Total Work Completed 785,712.59 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 785,712.59 146,630.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 146,630.29