Dept. of Trans. PROGRESS Serial No. Contract No. 11-025-09-17 07-3Y6004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 68% 07-LA-210-R0.4/R5.9 Federal Project: NONE Progress payment No. 02 Payment period ending: 01-20-11 POWELL CONSTRUCTORS INC 1355 BROOKS STREET UNIT F ONTARIO CA 91762 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 221,562.50 69,557.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 57,547.07 0.00 4. Earned Subject to Retention 279,109.57 69,557.50 5. Mobilization 40,000.00 2,000.00 6. Total Work Completed 261,562.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 319,109.57 71,557.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,557.50