Dept. of Trans. PROGRESS Serial No. Contract No. 12-082-09-07 07-3Y6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 81% 07-LA-210-R0.0/R9.9 Federal Project: ACBR-2101(805) IM-2101(805) Progress payment No. 04 Payment period ending: 03-20-12 CFCS TRUSTEE FOR J FRANCIS COMPANY 1330 ARNOLD DRIVE, SUITE 242 MARTINEZ, CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 669,349.46 399,109.88 2.a. Extra Work 3,560.42 969.68 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 672,909.88 400,079.56 5. Mobilization 34,000.03 1,700.00 6. Total Work Completed 706,909.91 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 706,909.91 401,779.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 401,779.56