Dept. of Trans. PROGRESS Serial No. Contract No. 10-145-12-24 07-3Y8704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 29% 07-VEN-232-0.4/4.1 Federal Project: NONE Progress payment No. 01 Payment period ending: 05-20-10 PAVEMENT COATINGS CO 10240 SAN SEVAINE WAY MIRA LOMA CA 91752 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 89,040.00 89,040.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 89,040.00 89,040.00 5. Mobilization 27,000.00 27,000.00 6. Total Work Completed 116,040.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 116,040.00 116,040.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,040.00