Dept. of Trans. PROGRESS Serial No. Contract No. 15-173-12-04 07-3Y9404 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 67% Location: Federal Project: 07-LA-405-16.4/19.5 NONE Progress payment No. 004 Payment period ending: 06-20-15 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 911,448.67 70,191.08 2. a. Extra Work 19,106.56 19,106.56 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 930,555.23 89,297.64 5. Mobilization 15,000.00 0.00 6. Total Work Completed 945,555.23 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 945,555.23 89,297.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 89,297.64