Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-294-13-49 07-4E1804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-110-10.3/23.8 Federal Project: NONE Progress payment No. 07 Payment period ending: 09-28-09 T AND G CONSTRUCTION INC 1227 BRIDGE STREET SUITE B YUBA CITY CA 95991 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 132,811.00 0.00 2.a. Extra Work 31,923.90 24,878.39 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 164,734.90 24,878.39 5. Mobilization 14,639.00 0.00 6. Total Work Completed 179,373.90 7. Deductions 0.00 1,500.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 179,373.90 26,378.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,378.39