Dept. of Trans. PROGRESS Serial No. Contract No. 07-024-10-11 07-4G5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 34% 07-VEN-150-8.7/ .0 Federal Project: ACST-P150(22) P-P150(22) Progress payment No. 07 Payment period ending: 01-20-07 BERKELEY ENGINEERING COMPANY P O BOX 7069 BERKELEY CA 94707 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,009.00 1,120.00 2.a. Extra Work 725,912.24 190,663.68 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 739,921.24 191,783.68 5. Mobilization 140,000.00 7,000.00 6. Total Work Completed 879,921.24 7. Deductions -2,281.25 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 877,639.99 198,783.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 198,783.68