Dept. of Trans. PROGRESS Serial No. Contract No. 06-298-13-26 07-4G6804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 81% 07-VEN-118-R23.8/R30.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-20-06 A AND R CONSTRUCTION CORP 20282 VIA MEDICI NORTHRIDGE CA 91326 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 249,569.90 129,618.40 2.a. Extra Work 3,700.00 3,700.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 253,269.90 133,318.40 5. Mobilization 9,235.00 461.75 6. Total Work Completed 262,504.90 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -12,663.50 -4,579.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 239,841.40 119,200.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 119,200.95