Dept. of Trans. PROGRESS Serial No. Contract No. 06-206-11-24 07-4G7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 68% 07-LA-39-22.5/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 07-20-06 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 02215 Total Estimate This Estimate 1. Contract Itms Without Mobil. 309,749.50 53,339.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 309,749.50 53,339.30 5. Mobilization 49,000.00 0.00 6. Total Work Completed 358,749.50 7. Deductions 8. a.Contract Retentions -15,487.48 -2,666.97 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 343,262.02 50,672.33 10. Reduction Amt to Escrow 11. Payment to Escrow 15,480.00 12. Net Pymt. this Estimate 50,672.33