Dept. of Trans. PROGRESS Serial No. Contract No. 06-298-07-12 07-4G7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-39-22.5/ .0 Federal Project: NONE Progress payment No. 06 Payment period ending: 10-20-06 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 02215 Total Estimate This Estimate 1. Contract Itms Without Mobil. 437,461.50 1,062.50 2.a. Extra Work 4,191.41 0.00 b. Adjustment Comp. 30,058.80 0.00 3. Materials on Hand 4. Earned Subject to Retention 471,711.71 1,062.50 5. Mobilization 49,000.00 0.00 6. Total Work Completed 520,711.71 7. Deductions 8. a.Contract Retentions -23,585.59 -53.13 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 497,126.12 1,009.37 10. Reduction Amt to Escrow 11. Payment to Escrow 23,530.00 12. Net Pymt. this Estimate 1,009.37