Dept. of Trans. PROGRESS Serial No. Contract No. 04-238-13-19 07-4H1004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-110-R3.3/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-20-04 HIGHLAND CONSTRUCTION INC 133 NORTH PIXLEY STREET ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 355,790.00 1,500.00 2.a. Extra Work 4,202.50 0.00 b. Adjustment Comp. 3,941.28 3,941.28 3. Materials on Hand 4. Earned Subject to Retention 363,933.78 5,441.28 5. Mobilization 46,600.00 0.00 6. Total Work Completed 410,533.78 7. Deductions -4,575.00 0.00 8. a.Contract Retentions -18,196.69 -272.06 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 387,762.09 5,169.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,169.22