Dept. of Trans. PROGRESS Serial No. Contract No. 04-238-13-19 07-4H1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 85% 07-LA-5953 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-04 HIGHLAND CONSTRUCTION INC 133 NORTH PIXLEY STREET ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 136,755.00 129,755.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 136,755.00 129,755.00 5. Mobilization 25,000.00 25,000.00 6. Total Work Completed 161,755.00 7. Deductions -10,193.00 -5,693.00 8. a.Contract Retentions -6,837.75 -6,137.75 b. Unsatisfactory Prog. -6,487.75 -6,487.75 c. Reduction after 95% Comp. 9. Total pay to Contractor 138,236.50 136,436.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,436.50