Dept. of Trans. PROGRESS Serial No. Contract No. 05-171-18-03 07-4H3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 94% 07-LA-105-2.6/2.6 Federal Project: NONE Progress payment No. 09 Payment period ending: 06-20-05 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 239,192.40 19,730.50 2.a. Extra Work 14,484.59 -906.83 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 253,676.99 18,823.67 5. Mobilization 24,000.00 0.00 6. Total Work Completed 277,676.99 7. Deductions 8. a.Contract Retentions -12,683.85 -941.18 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 264,993.14 17,882.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,882.49