Dept. of Trans. PROGRESS Serial No. Contract No. 06-171-16-12 07-4H5704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 35% 07-VEN-126-5.0/6.4 Federal Project: NONE Progress payment No. 01 Payment period ending: 06-20-06 RSB GROUP INC 94 SUMMERSTONE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,527.00 21,527.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 21,527.00 21,527.00 5. Mobilization 16,500.00 16,500.00 6. Total Work Completed 38,027.00 7. Deductions -8,415.30 -8,415.30 8. a.Contract Retentions -2,152.70 -2,152.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,459.00 27,459.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,459.00