Dept. of Trans. PROGRESS Serial No. Contract No. 02-327-10-28 07-4H8004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 100% 07-LA-39-28.0/44.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 11-20-02 MODERN ALLOYS, INC. 11172 WESTERN AVENUE STANTON, CA 90680 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,800.00 0.00 2.a. Extra Work 680,424.07 413,194.58 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 694,224.07 413,194.58 5. Mobilization 6. Total Work Completed 694,224.07 7. Deductions 8. a.Contract Retentions -44,000.00 -15,897.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 650,224.07 397,297.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 397,297.53