Dept. of Trans. PROGRESS Serial No. Contract No. 05-025-09-01 07-4H8704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-14-28.4/28.4 Federal Project: NONE Progress payment No. 06 Payment period ending: 01-20-05 STEVEN R RODGERS GENERAL ENGINEERING AND BUILDING CONTRACTOR 21558 PLACERITA CANYON ROAD NEWHALL CA 91321 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 216,290.60 420.00 2.a. Extra Work 13,129.27 11,633.42 b. Adjustment Comp. 6,456.25 1,954.90 3. Materials on Hand 4. Earned Subject to Retention 235,876.12 14,008.32 5. Mobilization 25,000.00 0.00 6. Total Work Completed 260,876.12 7. Deductions -1,956.82 0.00 8. a.Contract Retentions -11,793.81 -700.42 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 247,125.49 13,307.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,307.90