Dept. of Trans. PROGRESS Serial No. Contract No. 07-171-11-33 07-4J3804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 80% 07-LA-5-25.9/26.3 Federal Project: NONE Progress payment No. 04 Payment period ending: 06-20-07 O DONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 472,740.00 195,611.00 2.a. Extra Work 701.49 701.49 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 473,441.49 196,312.49 5. Mobilization 35,000.00 0.00 6. Total Work Completed 508,441.49 7. Deductions 8. a.Contract Retentions -23,672.07 -9,815.62 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 484,769.42 186,496.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 186,496.87