Dept. of Trans. PROGRESS Serial No. Contract No. 09-296-11-21 07-4K1504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 56% 07-LA-101-14.4/ .0 Federal Project: NONE Progress payment No. 07 Payment period ending: 10-20-09 L H ENGINEERING CO INC 708 N VALLEY STREET NO Q ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 861,734.30 -20,792.70 2.a. Extra Work 69,850.57 35,090.11 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 931,584.87 14,297.41 5. Mobilization 20,000.00 0.00 6. Total Work Completed 951,584.87 7. Deductions -17,500.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 934,084.87 14,297.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,297.41